Action of the ‘Przy Metrze’ Group no. 1

A group of consumers – parties to the financing agreements concluded with the defendant – represented by the Municipal Consumer Ombudsman of the City Council of the Capital City of Warsaw vs. housing cooperative in Warsaw.

Action for payment on the grounds of return of the undue performance in the form of amounts paid by group members for the adjustment of the sale prices of residential units, together with penalty interest, paid on the basis of contractual clauses declared to be abusive (judgment of the Regional Court in Warsaw 17th Competition and Consumer Protection Division of 20th April 2011, XVII AmC 1782/09).

38 group members

The case finally and validly concluded after the proceedings before the court of 1st instance.

3rd STAGE
  • Decision of the Regional Court in Warsaw 3rd Civil Division of 25th May 2016, III C 976/12 – discontinuing the appeal proceedings brought by the defendant’s appeal against the judgment of the Regional Court in Warsaw 3rd Civil Division of 2nd March 2016, III C 976/12, following the withdrawal of the appeal by the defendant
  • Judgment of the Regional Court in Warsaw 3rd Civil Division of 2nd March 2016, III C 976/12
  • The hearing of 2nd March 2016
  • The hearing of 29th Feburary 2016
  • The hearing of 25th Feburary 2016
  • The hearing of 11th January 2016
  • The hearing of 28th December 2015
  • The hearing of 16th December 2015
2nd STAGE
  • The hearing of 21st October 2014
1st STAGE
  • Statement of claims filed on: 4th September 2012